c0078-Bell-Barn-Restoration-473-Dan-Loran-Dec-03,-2009
c0080-Bell-Barn-Restoration-475-Heaters-Going-Inside-Dan-Loran-Dec-04,-2009
c0097 Bell Barn Restoration 502 Dan Loran 16 Dec 2009
16 December 2009 - It is bitterly cold in southern Saskatchewan, with the temperature around the -30 to -40 C range, and wind chills a low as -50. Feels like mid-February.
c0101-Bell-Barn-Restoration-506-Dan-Loran-Dec-21,-2009
c0105-Bell-Barn-Restoration-510-Dan-Loran-Dec-21,-2009
c0114-Bell-Barn-Restoration-5232-Dan-Loran-4-Jan,-2010
c0131 Bell Barn Restoration 5642 Dan Loran 14 Jan 2010
14 January 2010 - With the onset of some milder weather, the carpenters are able to install roofing paper on the Cottage Washroom.
c0138 Bell Barn Restoration 5711 Dan Loran 18 Jan 2010
18 January 2010 - Carpenters install plywood sheathing on the walls of the back storage room in the Cottage Washroom.
c0148Bell Barn Restoration 5871 Dan Loran 20 Jan 2010
20 January 2010 - The exterior of the Cottage Washroom and Maintenance Building after installation of the front windows.
c0166 Bell Barn Restoration 793 25 March 2010 Dan Loran
25 March 2010 - A crew from Bonkowski Enterprises in Wapella starts to install the sheet metal roof on the Cottage washroom.
c0171 Bell Barn Restoration 798 25 March 2010 Dan Loran
25 March 2010 - Sheet metal is cut to size for installation on the Cottage Washroom roof.
c0172 Bell Barn Restoration 799 25 March 2010 Dan Loran
25 March 2010 - Metal sheets being installed on the roof of the Cottage Washroom.
c0175 Bell Barn Restoration 809 Dan Loran 29 March 2010
29 March 2010 - A painter start to paint the interior walls of the Cottage Washroom-Maintenance Building.
c0176 Bell Barn Restoration 810 Dan Loran 29 March 2010
29 March 2010 - Getting the door frames ready for painting in the Cottage Washroom.
c0180 Bell Barn Restoration 814 Dan Loran 29 March 2010
29 March 2010 - Mixing paint for use inside the Cottage Washroom-Maintenance Building.
c0192-Bell-Barn-Restoration-922-Very-Rainy-&-Windy-Dan-Loran-13-April-2010
c0194 Bell Barn Restoration 930 Dan loran 15 April 2010
15 April 2010 - A furnace will keep the Cottage Washroom-Maintenance Building heated to a minimum lever during the winter months
c0196 Bell Barn Restoration 932 Dan Loran 15 April 2010
15 April 2010 - Carpenters begin applying the Hardi-Plank exterior siding to the Cottage Washroom-Maintenance building.
c0197 Bell Barn Restoration 936 Dan Loran 19 April 2010
19 April 2010 - Metal guides help ensure that the Hardi-Plank board are installed at the same level as the siding is applied.
c0200 Bell Barn Restoration 954 Dan Loran 22 April 2010
22 April 2010 - The Cottage Washroom-Maintenance Building is now fully sided with horizontal Hardi-Planks.